This section includes InterviewSolutions, each offering curated multiple-choice questions to sharpen your knowledge and support exam preparation. Choose a topic below to get started.
| 1. |
In long wall-short wall method, the length of the long wall is calculated after the addition of _________ to its centre line length at each end.(a) Breadth(b) Half breadth(c) Height(d) Half-heightI got this question in an internship interview.Question is taken from Estimation and Costing topic in division Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» The correct OPTION is (b) HALF BREADTH |
|
| 2. |
As per IS 3861-1966, which of the following areas should not be included while calculating the plinth area of a building?(a) Porches of non-cantilever type(b) Area of barsati at terrace level(c) Area of walls at floor level(d) Area of loftsI got this question in an online interview.I'm obligated to ask this question of Types of Estimates in division Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» Right option is (d) Area of lofts |
|
| 3. |
Single units work such as doors and windows are expressed in ________(a) numbers(b) metres(c) m^2(d) m^3The question was asked in examination.My doubt stems from Rate Analysis in chapter Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» Right CHOICE is (a) NUMBERS |
|
| 4. |
Works like whitewashing and plastering are measured in ________(a) m^2(b) Metres(c) Litres(d) m^3The question was posed to me in an interview for internship.The doubt is from Rate Analysis topic in section Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» The CORRECT option is (a) m^2 |
|
| 5. |
Work consisting of linear measurements like fencing which involve lengths is measured in __________(a) Kilograms(b) Running metres(c) m^2(d) m^3I had been asked this question in an online interview.This question is from Rate Analysis in chapter Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» The correct choice is (b) RUNNING metres |
|
| 6. |
In partly centre line and partly cross wall method, the centre line method is applied to _______(a) External walls(b) Internal walls(c) Thick walls(d) Thin wallsI got this question during an online interview.My query is from Estimation and Costing in portion Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» The correct option is (a) EXTERNAL walls |
|
| 7. |
In the cubical contents method, the cost of a structure is computed by the multiplication of total cubic contents and _______(a) Area of building(b) Volume of building(c) Local cubic rate(d) Length of buildingThis question was posed to me by my college professor while I was bunking the class.My doubt is from Types of Estimates in section Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» The correct choice is (c) LOCAL CUBIC rate |
|
| 8. |
Calculate the number of cement bags required for RCC (1:2:4) for 15 m^3 of work.(a) 24.6(b) 38.9(c) 56.7(d) 93.8I got this question during an online interview.My doubt is from Labour and Rate Analysis topic in chapter Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» CORRECT choice is (d) 93.8 The best explanation: The quantity of cement required is [1/(1+2+4)] x 1.52 x 15 m^3 i.e. 3.257 m^3. SP weight of concrete is 1440 KG/m^3 and the weight of one cement BAG is 50 kg. Therefore, the number of cement bags required for RCC (1:2:4) for 15 m^3 of WORK is 3.257 x 1440/50 = 93.8 bags. |
|
| 9. |
The quantity of coarse aggregate required for RCC (1:3:6) for 20 cubic metres of work is ________(a) 18.24 m^3(b) 15.23 m^3(c) 24.87 m^3(d) 32.45 m^3The question was posed to me in my homework.The query is from Labour and Rate Analysis in portion Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» The correct choice is (a) 18.24 m^3 |
|
| 10. |
Calculate the number of cement bags required for 2500 kg of cement.(a) 50(b) 100(c) 500(d) 200I got this question by my college director while I was bunking the class.The question is from Labour and Rate Analysis in division Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» The CORRECT option is (a) 50 |
|
| 11. |
In long wall-short wall method, the length of the short wall generally increases from earthwork to brickwork in the superstructure.(a) True(b) FalseI had been asked this question in a national level competition.The question is from Estimation and Costing in division Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» The CORRECT answer is (b) False |
|
| 12. |
The rates of materials used for government works are approved by _________(a) Executive Board(b) SDO(c) Elective Board(d) Board of Chief EngineersThis question was addressed to me during an interview.The doubt is from Labour and Rate Analysis topic in division Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» Correct CHOICE is (d) Board of Chief Engineers |
|
| 13. |
In earthwork calculations, how many lifts are to be paid to the contractor when the earth is to be lifted for 4.5 metres?(a) Four(b) Eight(c) Twelve(d) SixteenThe question was posed to me by my school principal while I was bunking the class.My doubt stems from Estimation and Costing topic in section Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» The CORRECT answer is (a) Four |
|
| 14. |
For the preparation of approximate estimates, cubical contents method is more accurate than the unit base method and plinth area method.(a) True(b) FalseThis question was addressed to me in exam.This key question is from Types of Estimates topic in division Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» The correct choice is (a) True |
|
| 15. |
The concrete used for cement concrete roads is of grade ___________(a) M 10(b) M 15(c) M 20(d) M 35The question was posed to me by my school teacher while I was bunking the class.My doubt stems from Labour and Rate Analysis in chapter Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» Correct OPTION is (b) M 15 |
|
| 16. |
The centre line method is suitable for walls having ________(a) Different cross-sections(b) Similar cross-sections(c) Same weights(d) Same materialsThe question was posed to me in an interview for internship.Query is from Estimation and Costing topic in chapter Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» The correct answer is (b) Similar cross-sections |
|
| 17. |
In the case of works which require some special types of equipment, an amount of ______ percent of the estimated cost is given.(a) 1-2(b) 5-9(c) 12-18(d) 16-20I got this question during an online exam.Enquiry is from Types of Estimates topic in chapter Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» Right ANSWER is (a) 1-2 |
|
| 18. |
Which of the following data is not required to prepare an estimate?(a) Amplitude(b) Drawings(c) Specifications(d) RatesThis question was posed to me in an internship interview.I'm obligated to ask this question of Types of Estimates topic in chapter Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» RIGHT option is (a) Amplitude The BEST explanation: For preparing an estimate, data such as drawings, detailed specifications, rates, ETC. is required. The drawings needed to prepare the estimate include plans, sections, ELEVATIONS, etc. |
|
| 19. |
Which of the following is not a classification of labour?(a) Skilled first class(b) Skilled second class(c) Unskilled(d) Unskilled fourth classThe question was posed to me in exam.Asked question is from Labour and Rate Analysis in division Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» The correct answer is (d) Unskilled fourth class |
|
| 20. |
Which of the following is the correct order of stages of estimation of concrete roads?(a) Earthwork excavations, cement concrete for the base course (1:4:8) and cement concrete for wearing course (1:2:8)(b) Earthwork excavations, cement concrete for wearing course (1:4:8) and cement concrete for the base course (1:2:8)(c) Earthwork excavations, cement concrete for the base course (1:6:9) and cement concrete for wearing course (1:7:9)(d) Cement concrete for the base course (1:2:3), cement concrete for wearing course (2:7:9) and earthwork excavationsI had been asked this question by my school principal while I was bunking the class.The question is from Labour and Rate Analysis in section Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» Right option is (a) Earthwork excavations, cement CONCRETE for the base course (1:4:8) and cement concrete for wearing course (1:2:8) |
|
| 21. |
Unit of measurement of asbestos cement sheet roofing is __________(a) Sqm(b) Kilograms(c) Metres(d) NumberI have been asked this question by my college director while I was bunking the class.I want to ask this question from Rate Analysis topic in division Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» Right CHOICE is (a) Sqm |
|
| 22. |
To get the quantities, the lengths found using the long wall-short wall method are multiplied with _________(a) Width(b) Weight(c) Thickness(d) Breadth and depthThe question was posed to me at a job interview.I need to ask this question from Estimation and Costing topic in portion Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» CORRECT choice is (d) Breadth and depth To explain: To get the QUANTITIES, the lengths FOUND using the long wall-short wall method are multiplied with breadth and depth. In this method, the centre line lengths of the individual walls are calculated first to get the LENGTH of the short wall and the long wall. |
|
| 23. |
Works like earthwork and cement concrete are measured in ________(a) Square metres(b) Metres(c) Litres(d) Cubic metresI have been asked this question during a job interview.The above asked question is from Rate Analysis in section Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» The CORRECT CHOICE is (d) Cubic metres |
|
| 24. |
Which of the following is not a method of working out quantities like earthwork and brickwork in plinth?(a) Long wall-short wall method(b) Centre line method(c) Thick wall – thin wall method(d) Partly centre line and short wall methodI have been asked this question in an interview for job.I want to ask this question from Estimation and Costing in chapter Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» The correct answer is (d) Partly CENTRE line and short wall method |
|
| 25. |
The quantity of sand required for RCC (1:2:4) for 15 cubic metres of work is ___________(a) 4.76 m^3(b) 10.32 m^3(c) 8.43 m^3(d) 6.51 m^3This question was addressed to me during an online exam.I'm obligated to ask this question of Labour and Rate Analysis topic in section Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» Correct choice is (d) 6.51 m^3 |
|
| 26. |
Which of the following is not a method used for preparing approximate estimates?(a) Cubical contents method(b) Unit base method(c) Plinth area method(d) Cylindrical base methodI have been asked this question by my school principal while I was bunking the class.The question is from Types of Estimates topic in chapter Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» Correct answer is (d) Cylindrical base method |
|
| 27. |
While fixing rate per unit of an item, the quantity of materials and labour needed for one unit of an item are strictly per __________(a) Special Data Book(b) Standard Data Book(c) Special Data Record(d) Specific Data RecordThe question was posed to me in final exam.Origin of the question is Types of Estimates topic in chapter Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» Correct option is (b) Standard Data Book |
|
| 28. |
Estimating is the technique of calculating the various quantities and is needed for controlling the expenditure during the execution of the work.(a) True(b) FalseThe question was asked during a job interview.My enquiry is from Types of Estimates in division Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» Right choice is (a) True |
|
| 29. |
In the plinth area method, the cost of construction is computed by the multiplication of ________(a) Plinth length and rate(b) Plinth breadth and rate(c) Plinth area and plinth area rate(d) Plinth volume and plinth length rateI have been asked this question in final exam.The above asked question is from Types of Estimates topic in section Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» The correct choice is (c) PLINTH area and plinth area rate |
|
| 30. |
The rules for measurement of all items are described in _______(a) IS-1993(b) IS-1896(c) IS-1200(d) IS-1987I got this question in final exam.Enquiry is from Rate Analysis topic in portion Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» The correct OPTION is (C) IS-1200 |
|
| 31. |
Unit of measurement of rainwater pipe is ________(a) Cum(b) Litres(c) Number(d) Running metresI got this question in an interview for job.I would like to ask this question from Rate Analysis in division Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» RIGHT CHOICE is (d) RUNNING METRES Easiest explanation: Unit of measurement of rainwater pipe is running metres. The unit of payment of rainwater pipes is PER RM. |
|
| 32. |
Unit of measurement of iron holdfasts in steelwork is ___________(a) Sqm(b) Number(c) Metres(d) QuintalThis question was addressed to me by my college professor while I was bunking the class.Query is from Rate Analysis topic in division Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» Right CHOICE is (d) Quintal |
|
| 33. |
Unit of measurement for damp proof course is ____________(a) Sqm(b) Cum(c) Number(d) KgThe question was asked during an internship interview.Asked question is from Rate Analysis in division Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» The correct CHOICE is (a) Sqm |
|
| 34. |
In long wall-short wall method, the wall along the length of the room is said to be the short wall.(a) True(b) FalseThe question was posed to me at a job interview.The question is from Estimation and Costing in portion Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» Right choice is (b) False |
|
| 35. |
As per the rules for measurement of items, it is specified that the areas should be measured to the nearest ________(a) 0.1 sq m(b) 0.25 sq m(c) 0.01 sq m(d) 0.85 sq mI had been asked this question in an interview for internship.My question comes from Rate Analysis topic in section Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» The correct CHOICE is (c) 0.01 sq m |
|
| 36. |
The process of working out the cost per unit of each item is known as _________(a) Work(b) Sheet(c) Data(d) AnalysisI got this question by my college director while I was bunking the class.Asked question is from Types of Estimates topic in section Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» Correct option is (C) Data |
|
| 37. |
The unit of measurement of pointing, painting and varnishing (no. of coats specified) is cum.(a) True(b) FalseThe question was asked in exam.This question is from Rate Analysis in division Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» Correct OPTION is (b) False |
|
| 38. |
The unit of payment of cement concrete in lintels is _________(a) Per sqm(b) Per cum(c) Quintal(d) KilogramsThe question was asked by my school teacher while I was bunking the class.The origin of the question is Labour and Rate Analysis topic in chapter Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» Correct answer is (b) Per cum |
|
| 39. |
Which of the following is not a lumpsum item in the estimate?(a) Architectural features(b) Water supply and sanitary arrangements(c) Masonry items(d) Electrical installationsThis question was posed to me during an online interview.My query is from Estimation and Costing topic in division Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» Correct answer is (c) Masonry items |
|
| 40. |
In earthwork calculations, the average horizontal distance between the centre of deposition and the centre of excavation is known as ___________(a) Lift(b) Flooring(c) Lead(d) EmbankmentThe question was asked in semester exam.Origin of the question is Estimation and Costing topic in chapter Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» The correct ANSWER is (c) Lead |
|