Which of the following is not a method used for preparing approximate estimates?(a) Cubical contents method(b) Unit base method(c) Plinth area method(d) Cylindrical base methodI have been asked this question by my school principal while I was bunking the class.The question is from Types of Estimates topic in chapter Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» Correct answer is (d) Cylindrical base method |
|