Calculate the number of cement bags required for RCC (1:2:4) for 15 m^3 of work.(a) 24.6(b) 38.9(c) 56.7(d) 93.8I got this question during an online interview.My doubt is from Labour and Rate Analysis topic in chapter Rate Analysis, Estimation and Costing of Construction & Building Materials

Answer» CORRECT choice is (d) 93.8

The best explanation: The quantity of cement required is [1/(1+2+4)] x 1.52 x 15 m^3 i.e. 3.257 m^3. SP weight of concrete is 1440 KG/m^3 and the weight of one cement BAG is 50 kg. Therefore, the number of cement bags required for RCC (1:2:4) for 15 m^3 of WORK is 3.257 x 1440/50 = 93.8 bags.