1.

In earthwork calculations, the average horizontal distance between the centre of deposition and the centre of excavation is known as ___________(a) Lift(b) Flooring(c) Lead(d) EmbankmentThe question was asked in semester exam.Origin of the question is Estimation and Costing topic in chapter Rate Analysis, Estimation and Costing of Construction & Building Materials

Answer»

The correct ANSWER is (c) Lead

For explanation I would say: In earthwork calculations, the average horizontal distance between the CENTRE of deposition and the centre of excavation is known as lead. Its UNIT is 50 m.