Saved Bookmarks
| 1. |
Which of the following is the correct order of stages of estimation of concrete roads?(a) Earthwork excavations, cement concrete for the base course (1:4:8) and cement concrete for wearing course (1:2:8)(b) Earthwork excavations, cement concrete for wearing course (1:4:8) and cement concrete for the base course (1:2:8)(c) Earthwork excavations, cement concrete for the base course (1:6:9) and cement concrete for wearing course (1:7:9)(d) Cement concrete for the base course (1:2:3), cement concrete for wearing course (2:7:9) and earthwork excavationsI had been asked this question by my school principal while I was bunking the class.The question is from Labour and Rate Analysis in section Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» Right option is (a) Earthwork excavations, cement CONCRETE for the base course (1:4:8) and cement concrete for wearing course (1:2:8) |
|