For the preparation of approximate estimates, cubical contents method is more accurate than the unit base method and plinth area method.(a) True(b) FalseThis question was addressed to me in exam.This key question is from Types of Estimates topic in division Rate Analysis, Estimation and Costing of Construction & Building Materials |
|
Answer» The correct choice is (a) True |
|