1.

__________ are the cofferdams which can be lifted, floated and placed in another position as soon as its purpose is served.(a) Dike cofferdam(b) Double wall cofferdam(c) Suspended cofferdam(d) Single wall cofferdam

Answer» Correct option is (c) Suspended cofferdam

Best explanation: Suspended cofferdams are also known as the movable cofferdams. The suspended cofferdams may take up any forms. In one form, it consists of a hollow steel cylinder which can be used to prepare a temporary enclosed space for the construction work.
2.

In __________ type of cofferdam consists of a mixture of sand and clay which is filled in a bag and placed instead of earth or rock to form a cofferdam.(a) Cellular cofferdam(b) Earth dikes(c) Rock dikes(d) Sand-bag dikes

Answer» Right choice is (d) Sand-bag dikes

Explanation: The sand-bag dykes or Sand-bag cofferdams are useful for small depth of water. The individual bags are laid in courses as in case of masonry work and the joints are filled with puddle.
3.

Identify the Method used for the dewatering of the foundation trenches.(a) Pumping(b) Freezing process(c) Electro osmosis process(d) Well Point System

Answer» Correct answer is (d) Well Point System

Easiest explanation: Well Point System consists of a well points, riser, swinger arm, and header. The area to be devoted is surrounded by number of well points. The minimum spacing between the well points is 1 m.
4.

A _______ is defined as a temporary structure which is constructed so as to remove water and/or soil from an area and make it possible to carry on the construction work under reasonably dry conditions.(a) Cofferdam(b) Foundation(c) Caisson(d) SpillwayThe question was posed to me in homework.This key question is from Cofferdam and Caisson topic in chapter Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»

Correct answer is (a) COFFERDAM

To EXPLAIN I would say: The cofferdam is generally constructed at the SITE of WORK. The cofferdam should be reasonably watertight. It MAY either raised on the impervious soil or may be extended to impervious strata through pervious soils. It should be noted that absolute water tightness is not desired in a cofferdam.

5.

The ___________ is made of steel sheet piles and this type of cofferdam is proved successful in unwatering large areas.(a) Suspended cofferdam(b) Cellular cofferdam(c) Dikes(d) Concrete cofferdamI have been asked this question during an interview for a job.Query is from Cofferdam and Caisson topic in chapter Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»

The correct answer is (B) Cellular cofferdam

The best explanation: Cellular cofferdam consists of diaphragm CELLS or circular cells or modified circular cells or cloverleaf cells. In case of circular cofferdams with diaphragm cells, the series of ARCS are CONNECTED to straight cross wall. The radius of arcs is GENERALLY made equal to the distance between the cross-walls.

6.

The ________ can be adopted as an aid in construction to stop rock movements and to increase the permeability of the strata as in the case of oil wells.(a) Chemical grouting(b) Cement grouting(c) Pumping(d) Well Point SystemI got this question during an interview.My question comes from Deep Excavations topic in section Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»

Correct choice is (a) Chemical GROUTING

To explain I would say: As the chemical grouting has been DEVELOPED recently, the precise information of its long-term after effects is not AVAILABLE. Hence it has yet not become an ESTABLISHED TECHNIQUE as the conventional grouting.

7.

Identify the type of pile.(a) Raymond standard concrete pile(b) Raymond step taper concrete pile(c) Mac Arthur pile(d) Base driven pileThe question was posed to me by my school teacher while I was bunking the class.The doubt is from Different Types of Pile topic in chapter Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»

Right option is (b) Raymond STEP taper concrete pile

For explanation: Raymond step taper concrete pile consists of Steel sections of SUITABLE length. The bottom of the first shell to be driven is closed by a flat steel plate. The DIAMETER of pile increases in steps at the rate of 25 mm for each successive shell section.

8.

The organic Chemicals include epoxy resin, polyester resin and other resins are used in which method of dewatering of the foundation trenches?(a) Well Point System(b) Cement grouting(c) Chemical grouting(d) Electro osmosis processThe question was posed to me in exam.My question is from Deep Excavations in division Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»

Right answer is (c) Chemical grouting

To elaborate: In 1925, H.J. Joosten, a Dutch mining ENGINEER, ADOPTED for the first time the chemical grouting. He used concentrated SOLUTION of sodium silicate and calcium chloride as ELECTROLYTE. According to him, the chemical MUST be able to modify the properties of soil as desired or expected.

9.

When the area to be enclosed is large, it becomes essential to provide the _________ construction so as to give stability to the cofferdam.(a) Single wall cofferdam(b) Cellular cofferdam(c) Double wall cofferdam(d) Suspended cofferdamThe question was asked in my homework.My question is from Cofferdam and Caisson in portion Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»

Right answer is (c) Double wall COFFERDAM

To EXPLAIN I would say: Double wall cofferdam was frequently used on the river Ohio in USA and hence, it derives its name as Ohio river type cofferdam. It is cheap and can be BUILT up rapidly l. It is suitable for hard bed where there is no PROBLEM of erosion. This type of cofferdam is unsuitable for deep water.

10.

From given below, which method for the dewatering of foundation trenches is portable and can be easily moved when required?(a) Pumping(b) Well Point System(c) Freezing process(d) Electro osmosis processThis question was addressed to me by my college director while I was bunking the class.My query is from Deep Excavations in portion Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»

Right ANSWER is (a) Pumping

Easiest explanation: In pumping METHOD, the pumps are installed along the foundation trenches at suitable POINTS. The water gaining ACCESS to the trenches is pumped out. These pumps are portable so that it can be EASILY moved as and when required.

11.

Identify the given pile driving formula.(a) Dutch formula(b) Hiley formula(c) Engineering News formula(d) Ritter formulaThis question was addressed to me by my college professor while I was bunking the class.The query is from Pile Driving Formulas topic in chapter Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»

Correct ANSWER is (b) Hiley formula

Easy explanation: Above given formula is Hiley formula. This formula is widely used in determining the safe load on pile.

Where, E = EFFICIENCY of hammer.

K = COEFFICIENT of restitution.

12.

The __________ is found to be the most suitable material for the construction of caisson.(a) Timber(b) Cast iron(c) Steel(d) RCCThis question was posed to me during an interview.Enquiry is from Classification of Caissons topic in portion Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»

Correct answer is (c) Steel

To ELABORATE: Steel is USUALLY in the FORM of a double skin of Steel PLATING and the hollow space in then filled with cement concrete. Due to its strength and DURABILITY it is found to be most suitable material.

13.

Identify the type of pile.(a) Load bearing piles(b) Sand pile(c) Friction pile(d) Steel pipeThis question was addressed to me in class test.This is a very interesting question from Different Types of Pile in chapter Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer» RIGHT choice is (c) Friction pile

Easiest explanation: When loose soil EXTENDS to a great DEPTH, the piles are driven up to such a depth that the frictional resistance developed at the SIDES of the piles equals the load coming on the piles.
14.

Identify the type of Well Point System.(a) Vacuum system(b) Single stage system(c) Multi stage system(d) PumpingThis question was addressed to me in an internship interview.I want to ask this question from Deep Excavations in section Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»

The CORRECT answer is (a) Vacuum system

Explanation: The vacuum process is very much USEFUL and EFFECTIVE for inorganic and organic silts and very fine sand. But several weeks may be required to achieve CONSOLIDATION by this method.

15.

Identify the type of pile.(a) Mac Arthur pile(b) Base driven pile(c) Swage pile(d) Monotube pileI have been asked this question in an international level competition.My question is taken from Different Types of Pile in section Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»

Right option is (a) Mac ARTHUR pile

The explanation is: In Mac Arthur pile, a heavy steel CASING with a core is driven into the ground as SHOWN in given figure. When the desired depth is REACHED, the core is withdrawn and a CORRUGATED steel shell is placed in the casing.

16.

Identify the missing data in the below figure.(a) Ranger(b) Wale(c) Sheathing(d) BracingThis question was posed to me in a national level competition.Asked question is from Deep Excavations in section Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer» RIGHT answer is (d) BRACING

The best explanation: The diagonal piece of TIMBER used to GIVE rigidity to the Framework is known as the Bracing. These MEMBERS are mostly subjected to compressive forces.
17.

A __________ are open at bottom and closed at top.(a) Cylinders(b) Wells(c) Box Caisson(d) Pneumatic caissonsI got this question in exam.My question comes from Classification of Caissons in portion Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»

Right choice is (d) PNEUMATIC caissons

The explanation is: The pneumatic caissons are adopted when the depth of water is more than 12 metres or so. The MAXIMUM depth of water upto which pneumatic caissons can be USED is limited from the CONSIDERATION of health of the workers.

18.

___________ is to be incorporated as a part of a permanent structure which have been proved to be economical.(a) Concrete cofferdam(b) Suspended cofferdam(c) Single wall cofferdam(d) Cellular cofferdamThe question was asked in an international level competition.Question is taken from Cofferdam and Caisson topic in division Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»

The correct option is (a) Concrete cofferdam

Explanation: Concrete cofferdams are actually small concrete dams and they have been USED ECONOMICALLY on many Jobs. The FRAMEWORK usually consists of precast RCC PILES and sheets. The main disadvantage of a concrete cofferdam is that it is costly.

19.

Identify the type of pile.(a) Swage pile(b) Base driven pile(c) Button bottom pile(d) Mac Arthur pileThis question was addressed to me in exam.My doubt is from Different Types of Pile in chapter Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»

Right option is (a) Swage PILE

The explanation: In Swage pile, a precast CONCRETE plug of slight conical shape provided at the bottom of a steel shell. These piles are used for HARD SOIL or at places where it is desired to have a WATERTIGHT shell before concrete is placed in the Shell.

20.

Identify the Method used for the dewatering of the foundation trenches.(a) Vacuum system(b) Single stage system(c) Pumping(d) Multi stage systemI had been asked this question in exam.I need to ask this question from Deep Excavations topic in section Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»

Right option is (d) Multi stage system

Best explanation: When the DEPTH of excavation EXCEEDS 5 M below the WATER table, the PROCESS of PROVIDING well Point is carried out in different stages known as Multi stage system.

21.

Which precautions to be taken in case of multistage system to achieve stability of the side slope?(a) Deep well pumps(b) Duplication of pumps(c) Connections(d) PumpingI got this question in quiz.I would like to ask this question from Deep Excavations in section Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»

The correct option is (a) Deep well pumps

To explain: In case of multistage SYSTEM of well points, the deep well pumps should be used when the INSTABILITY of the side slopes is EXPECTED. As deep well pumps are expensive, they are ADOPTED on important WORKS.

22.

In _______ arrangement, the vertical sheets are placed nearer or sometimes, touching each other.(a) Stay bracing(b) Box sheeting(c) Vertical sheeting(d) RunnerI had been asked this question in an interview for job.My question comes from Deep Excavations topic in section Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»

Right answer is (b) Box sheeting

To elaborate: The Box sheeting arrangement is adopted for loose SOIL. In this, the sheets are kept in position by LONGITUDINAL rows of WALES, usually 2 in numbers and then, the STRUTS are provided across the wales.

23.

The ___________ was used as a material for the construction of caisson in the early stages of development of Caisson.(a) Steel(b) Timber(c) Cast iron(d) RCCI got this question in an online interview.This intriguing question originated from Classification of Caissons topic in chapter Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer» RIGHT answer is (b) Timber

For explanation I would SAY: In OLD days, Timber was the cheapest material due to its availability in abundance. But this material is now practically not adopted mainly because of its bulk and the risk of Fire.
24.

__________ are the cofferdams which can be lifted, floated and placed in another position as soon as its purpose is served.(a) Dike cofferdam(b) Double wall cofferdam(c) Suspended cofferdam(d) Single wall cofferdamI had been asked this question in class test.Question is from Cofferdam and Caisson topic in chapter Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»

Correct option is (c) Suspended cofferdam

Best explanation: Suspended cofferdams are also known as the movable cofferdams. The suspended cofferdams may take up any FORMS. In one form, it consists of a hollow steel CYLINDER which can be used to PREPARE a temporary enclosed space for the CONSTRUCTION work.

25.

Identify the given pile driving formula.(a) Ritter formula(b) Major Sander formula(c) Kreutzer formula(d) Vulcan Iron Works formulaThe question was posed to me by my college director while I was bunking the class.My doubt is from Pile Driving Formulas topic in division Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»

Correct ANSWER is (b) Major Sander FORMULA

Explanation: Major Sander formula is the simplest form of pile driving formula using a factor of safety of 8. Where, R1 = safe LOAD on a pile in kg.

S = final SETTLEMENT of pile in cm.

26.

The ___________ obtain the bearing power of the piles by equating the soil resistance to the energy of the blow.(a) Static formulas(b) Dynamic formulas(c) Wave action theory(d) Empirical formulasThe question was posed to me in an international level competition.I'd like to ask this question from Pile Driving Formulas topic in chapter Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer» RIGHT option is (b) Dynamic formulas

For explanation I would say: Extreme CARE should be TAKEN while adopting dynamic formulas. There is no dynamic formula which can be applied for all the varying CONDITIONS of the work. Most of the dynamic formulas are BASED on some rational approach.
27.

The _______ can be effectively adopted for excavation in or at the foot of the slope of a hill.(a) Freezing process(b) Cement grouting(c) Pumping(d) Well Point SystemThe question was posed to me in class test.My question is from Deep Excavations in section Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»

The correct option is (a) Freezing process

The explanation: The freezing is a powerful versatile tool for foundation engineering for temporary ground support, groundwater control and structural underpinning. A PORTION of the slope is FROZEN and this POSITION act as a temporary Dam to support the SOIL and it prevents the earth slides.

28.

Identify the missing data.(a) Riser(b) Swinger arm(c) Header(d) HeadI got this question during an online interview.I would like to ask this question from Deep Excavations in section Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»

Right CHOICE is (a) Riser

For explanation I WOULD say: A Riser is a vertical PIPE driven in the ground. The well point is provided at the bottom end of the riser. The diameter of the Riser is about 40 mm to 50 mm.

29.

__________ is the simplest form of cofferdam.(a) Single wall cofferdam(b) Earth-fill cofferdam(c) Cellular cofferdam(d) Rock-fill cofferdamThe question was posed to me by my school teacher while I was bunking the class.This question is from Cofferdam and Caisson in chapter Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»

The correct choice is (b) Earth-fill cofferdam

Easy explanation: Earth dikes or Earth-fill cofferdams are limited to Shallow depth of WATER, say about 1200 MM to 1500 mm, with a low velocity of flow. It consists of an Earth BANK which is placed around the SITE to be enclosed.

30.

Identify the type of pile.(a) Under reamed pile(b) Pedestal pile(c) Simplex pile(d) Pressure pileThe question was posed to me during an online interview.The question is from Different Types of Pile in chapter Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»

Right ANSWER is (d) PRESSURE pile

Explanation: In Pressure pile, the compressed air is then admitted through the air Pipe and which is applied to RAISE the TUBE. Thus, the tube is lifted slightly and at the same time, the concrete is forced into the surrounding GROUND by compressed air.

31.

Identify the type of pile.(a) Pressure pile(b) Pedestal pile(c) Vibro pile(d) Simplex pileI got this question in exam.This intriguing question originated from Different Types of Pile topic in portion Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»
32.

From the below diagram, identify the Method used for the dewatering of the foundation trenches.(a) Pumping(b) Freezing process(c) Electro osmosis process(d) Well Point SystemThis question was addressed to me in homework.I would like to ask this question from Deep Excavations in chapter Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer» CORRECT choice is (d) Well Point System

Easiest explanation: Well Point System CONSISTS of a well points, riser, swinger arm, and header. The area to be devoted is surrounded by number of well points. The minimum spacing between the well points is 1 m.
33.

Identify the Method used for the dewatering of the foundation trenches.(a) Electro osmosis process(b) Chemical process(c) Cement grouting(d) Freezing processI had been asked this question in class test.Question is taken from Deep Excavations topic in chapter Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»

The CORRECT OPTION is (d) FREEZING process

The explanation: In the freezing process method, the area surrounding the EXCAVATION is frozen and THUS a solid wall of frozen Earth is formed. The principle of ground freezing is the use of refrigeration to convert in-situ pore water to Ice.

34.

Identify the missing data.(a) Wale(b) Strut(c) Bracing(d) SheetingThis question was addressed to me during an online exam.The above asked question is from Deep Excavations in section Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»

Correct answer is (a) Wale

Explanation: RANGER or Wale is the NAME given to the piece of timber which transfers the load from the SHEETING to the Strut. This piece of timber also acts as a supporting member for BRACING.

35.

A ________ is a caisson which is open at top as well as at bottom.(a) Well(b) Box Caisson(c) Pneumatic caissons(d) CofferdamThe question was asked by my college professor while I was bunking the class.My doubt stems from Classification of Caissons in division Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»

Right CHOICE is (a) Well

Easy explanation: Well is provided with a cutting edge at the bottom so as to facilitate sinking. The shape of a well is GENERALLY decided by the requirements of the superstructure, vertical and horizontal forces on well, base of the pier or abutment, cost of sinking, CHANCES of tilting and SHIFTING during execution, ETC.

36.

A _________ is an embankment of some material.(a) Wall(b) Intrusion(c) Dike(d) Rock-fillI have been asked this question in quiz.This interesting question is from Cofferdam and Caisson topic in portion Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»

The correct answer is (C) Dike

To explain I would SAY: The materials commonly employed for the construction of dike are earth, ROCK and sand bags. The dike are generally employed for a short duration, PARTICULARLY to ENABLE the construction of a more durable cofferdam behind them.

37.

The organic Chemicals include epoxy resin, polyester resin and other resins are used in which method of dewatering of the foundation trenches.(a) Well Point System(b) Cement grouting(c) Chemical grouting(d) Electro osmosis processThe question was asked by my school principal while I was bunking the class.The above asked question is from Deep Excavations in section Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»

The correct option is (c) Chemical GROUTING

For explanation I would say: In 1925, H.J. Joosten, a DUTCH mining engineer, adopted for the first time the chemical grouting. He used CONCENTRATED solution of sodium silicate and CALCIUM chloride as electrolyte.

38.

Identify the given type of Timbering.(a) Sheet piling(b) Runner(c) Stay bracing(d) Vertical sheetingThis question was posed to me during an online exam.The doubt is from Deep Excavations in section Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»
39.

An open _______ is a convenient form of foundation for Bridge piers.(a) Monoliths(b) Cylinder(c) Multiple wells(d) CofferdamThe question was asked in an internship interview.My question comes from Classification of Caissons topic in portion Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer» RIGHT option is (b) Cylinder

To explain I would say: Cylinder is used when depth of water is more than 12 meters or when it becomes ESSENTIAL go deep to avoid exposure of foundations due to scouring action of flowing water. The cylinder is a LIGHT shell which INVARIABLY become part of the permanent structure.
40.

The __________ equate the soil resistance to the bearing power of the pile.(a) Dynamic formulas(b) Wave action theory(c) Static formulas(d) Empirical formulasI got this question by my school teacher while I was bunking the class.This key question is from Pile Driving Formulas in section Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»

The correct choice is (c) STATIC formulas

The best explanation: To determine Static formulas, the SAMPLES of soils through which piles are to be DRIVEN are tested in the laboratory and properties of different soils are studied in detail. These results from the laboratory TESTS are then used to determine the bearing capacity of a pile of a given length, shape and size.

41.

Identify the type of pile.(a) Raymond step taper concrete pile(b) Friction pile(c) Raymond Standard concrete pile(d) Mac Arthur pileI got this question in final exam.My enquiry is from Different Types of Pile topic in chapter Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer» CORRECT ANSWER is (c) Raymond Standard CONCRETE pile

Explanation: Raymond standard concrete pile consists of a thin corrugated shell closed at the bottom. The shell is DRIVEN into the ground with a collapsible Steel mandrel core in it. When the desired depth is reached, the mandrel is COLLAPSED and withdrawn.
42.

Identify the type of pile.(a) Simplex pile(b) Simplex Alligator pile(c) Franki pile(d) Vibro pileThe question was asked in homework.The above asked question is from Different Types of Pile topic in portion Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»

Correct choice is (b) Simplex Alligator pile

Easy explanation: In Simplex Alligator jaw pile, the cast iron SHOE is PROVIDED by alligator jaw point. When CONCRETE is poured, the jaw opens and ALLOWS concrete to flow. In this TYPE of pile, the shoe does not remain in the ground.

43.

Identify the Method used for the dewatering of the foundation trenches.(a) Pumping(b) Providing sumps and side drains(c) Well Point System(d) Cement groutingI got this question in unit test.This interesting question is from Deep Excavations in division Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer» RIGHT answer is (b) Providing sumps and side drains

For explanation I would say: In providing sumps and side drains, the side drains are constructed ALONG the bottom of the foundation Trenches. The sumps are constructed at a distance of 45 M to 60 M and the side drains are given such as SLOPE that water is collected in the sumps.
44.

_________ is defined as the main plank which remains in contact with sides of Trench.(a) Sheeting(b) Wale(c) Sheathing(d) BracingI had been asked this question in semester exam.This question is from Deep Excavations topic in division Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»

The correct answer is (a) Sheeting

Explanation: The TERM SHEATHING is used to indicate vertical MEMBERS of timber in which directly resist PRESSURE from the side of a Trench.

45.

A ______ caisson is open at top and closed at bottom.(a) Wells(b) Pneumatic caissons(c) Cylinders(d) Box caissonsI have been asked this question in an internship interview.Query is from Classification of Caissons in chapter Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»

Right choice is (d) Box caissons

For explanation: Box CAISSON is merely a variation of the Suspended type cofferdam. The box caissons MAY be built of reinforced concrete, steel or TIMBER. Condition for box caisson is that the depth of water is about 6 METERS to 8 meters.

46.

A __________ consist of timber cribs.(a) Cellular cofferdam(b) Suspended cofferdam(c) Concrete cofferdam(d) Rock-filled crib cofferdamI got this question in an interview.I'm obligated to ask this question of Cofferdam and Caisson in chapter Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»

Right ANSWER is (d) Rock-filled crib COFFERDAM

To explain: A crib is a box or a CELL open at the bottom and it essentially consists of a framework of horizontal timbers laid in alternate courses. The Rock-filled crib cofferdam have been employed with success on many IMPORTANT Jobs. The IDEAL set of conditions favourable for this type of cofferdam is the depth of water is about 10 meters to 20 m.

47.

In __________ type of cofferdam consists of a mixture of sand and clay which is filled in a bag and placed instead of earth or rock to form a cofferdam.(a) Cellular cofferdam(b) Earth dikes(c) Rock dikes(d) Sand-bag dikesI have been asked this question in an online quiz.My question is taken from Cofferdam and Caisson in portion Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer» RIGHT choice is (d) Sand-bag dikes

Explanation: The sand-bag dykes or Sand-bag cofferdams are useful for SMALL DEPTH of water. The individual BAGS are laid in COURSES as in case of masonry work and the joints are filled with puddle.
48.

Identify the given pile driving formula.(a) Merriman formula(b) Ritter formula(c) Vulcan Iron Works formula(d) Kreutzer formulaI got this question in an international level competition.My question is taken from Pile Driving Formulas topic in section Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»

Correct answer is (b) Ritter formula

For EXPLANATION: Above given formula is Ritter formula. It is an important PILE driving dynamic formula. Where, R = ultimate load carrying capacity of pile in kg.

H = height of FREE fall of ram in case of drop hammer in CM.

S = final settlement of pile in cm.

49.

Identify the type of pile.(a) Load bearing pile(b) Friction pile(c) Cast iron pile(d) Timber pileI had been asked this question during an online exam.The doubt is from Different Types of Pile topic in chapter Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»

Correct answer is (a) Load bearing pile

Explanation: Load bearing piles penetrate through the soft SOIL and their bottom rest on a hard bed. Thus, they are end bearing piles and ACT as a column or piers. The soft GROUND through which the piles pass also give some lateral support and thus increases the load CARRYING capacity of the bearing piles.

50.

Identify the Method used for the dewatering of the foundation trenches.(a) Vacuum system(b) Single stage system(c) Multi stage system(d) PumpingI got this question by my college director while I was bunking the class.Asked question is from Deep Excavations topic in division Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»

The correct choice is (a) VACUUM system

The explanation is: The vacuum PROCESS is very much useful and effective for inorganic and ORGANIC silts and very fine sand. But several weeks may be required to achieve CONSOLIDATION by this method.