In _______ arrangement, the vertical sheets are placed nearer or sometimes, touching each other.(a) Stay bracing(b) Box sheeting(c) Vertical sheeting(d) RunnerI had been asked this question in an interview for job.My question comes from Deep Excavations topic in section Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»

Right answer is (b) Box sheeting

To elaborate: The Box sheeting arrangement is adopted for loose SOIL. In this, the sheets are kept in position by LONGITUDINAL rows of WALES, usually 2 in numbers and then, the STRUTS are provided across the wales.