Saved Bookmarks
| 1. |
Identify the Method used for the dewatering of the foundation trenches.(a) Pumping(b) Freezing process(c) Electro osmosis process(d) Well Point System |
|
Answer» Correct answer is (d) Well Point System Easiest explanation: Well Point System consists of a well points, riser, swinger arm, and header. The area to be devoted is surrounded by number of well points. The minimum spacing between the well points is 1 m. |
|