1.

Identify the Method used for the dewatering of the foundation trenches.(a) Vacuum system(b) Single stage system(c) Pumping(d) Multi stage systemI had been asked this question in exam.I need to ask this question from Deep Excavations topic in section Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»

Right option is (d) Multi stage system

Best explanation: When the DEPTH of excavation EXCEEDS 5 M below the WATER table, the PROCESS of PROVIDING well Point is carried out in different stages known as Multi stage system.