1.

Identify the missing data.(a) Wale(b) Strut(c) Bracing(d) SheetingThis question was addressed to me during an online exam.The above asked question is from Deep Excavations in section Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials

Answer»

Correct answer is (a) Wale

Explanation: RANGER or Wale is the NAME given to the piece of timber which transfers the load from the SHEETING to the Strut. This piece of timber also acts as a supporting member for BRACING.