Which precautions to be taken in case of multistage system to achieve stability of the side slope?(a) Deep well pumps(b) Duplication of pumps(c) Connections(d) PumpingI got this question in quiz.I would like to ask this question from Deep Excavations in section Deep Excavations, Pile Foundations and Caisson of Construction & Building Materials |
|
Answer» The correct option is (a) Deep well pumps |
|