The difference between the maximum time available and the actual time needed to perform an activity is known as _________(a) Free float(b) Independent float(c) Total float(d) Half floatI got this question at a job interview.I would like to ask this question from PERT and CPM in chapter Building Plans, PERT and CPM of Construction & Building Materials |
|
Answer» Correct ANSWER is (c) Total float |
|