Bar charts were modified later to obtain the milestone charts.(a) True(b) FalseI have been asked this question in an interview.The above asked question is from PERT and CPM in division Building Plans, PERT and CPM of Construction & Building Materials

Answer»

The CORRECT choice is (a) True

Best EXPLANATION: The various tools or techniques used for project management are bar CHARTS, milestone charts and network diagrams. Bar charts were modified LATER to obtain the milestone charts.