In bar charts, which colour is used to show the actual progress?(a) Red(b) Black(c) Blue(d) GreenI have been asked this question in an online quiz.My doubt stems from PERT and CPM topic in chapter Building Plans, PERT and CPM of Construction & Building Materials

Answer» RIGHT answer is (d) Green

Easiest explanation: In bar charts, different colours are sometimes filled in the bars for showing VARIOUS control information. For ACTUAL progress, green colour is used. For anticipated progress, black colour is used and for progress behind SCHEDULE, red colour is used.