In a network, a critical path is the time-wise shortest path.(a) True(b) FalseThis question was addressed to me in an interview for internship.The question is from PERT and CPM topic in portion Building Plans, PERT and CPM of Construction & Building Materials |
|
Answer» The CORRECT option is (B) False |
|