1.

According to the time estimates made by the PERT planners, the maximum time that would be needed to complete an activity is called as __________(a) The most likely time estimate(b) Optimistic time estimate(c) Pessimistic time estimate(d) Expected time estimateThis question was addressed to me in a job interview.This interesting question is from PERT and CPM topic in division Building Plans, PERT and CPM of Construction & Building Materials

Answer»

Right choice is (c) Pessimistic TIME estimate

Explanation: According to the time ESTIMATES made by the PERT planners, the MAXIMUM time that would be needed to complete an activity is called the pessimistic time estimate. This estimate does not include POSSIBLE effects of floods, earthquakes, etc.