The __________ of formwork plays a significant role in the cost of concrete.(a) Conditions(b) Work(c) Period(d) EconomyThe question was posed to me during an interview for a job.My question is taken from Components of Formwork in chapter Arches, Lintels, Stairs and Formwork of Construction & Building Materials

Answer»

Correct choice is (d) Economy

To ELABORATE: The cost of formwork VARIES from 30% to 40% of the cost of CONCRETE for ordinary structures and maybe go as HIGH as 50% to 60% for special structures are just dams, bridges, ETC.