Saved Bookmarks
| 1. |
The formwork for an ___________ consists of rows of the vertical post which carry small wooden beams at their tops.(a) RCC floors(b) RCC slab(c) RCC column(d) RCC beamThis question was posed to me during an interview for a job.Question is taken from Materials Used for Formwork topic in section Arches, Lintels, Stairs and Formwork of Construction & Building Materials |
|
Answer» RIGHT OPTION is (a) RCC floors Easy explanation: The formwork for an RCC floor consists of a SKELETON to receive the concrete. The planks for slab are placed on these BEAMS. The boxes for beams are prepared from TWO sides and one bottom. |
|