The boxes for beams are play prepared from ________ sides and ________ bottom in formwork for an RCC floor.(a) One, One(b) Two, Two(c) One, Two(d) Two, OneI have been asked this question in an interview for job.I'd like to ask this question from Components of Formwork topic in portion Arches, Lintels, Stairs and Formwork of Construction & Building Materials |
|
Answer» Correct option is (c) One, Two |
|