1.

In _________ method, the piles are driven along both the sides of existing wall and the needle in the form of pile caps are provided through the existing one.(a) Pit method(b) Pile method(c) Miscellaneous method(d) VibroflotationThis question was posed to me by my school principal while I was bunking the class.This key question is from Underpinning and its Types in section Scaffolding, Shoring and Underpinning of Construction & Building Materials

Answer»

The CORRECT choice is (b) Pile method

Easy explanation: Pile method is useful in clayey soils and for waterlogged areas and for WALLS CARRYING heavy loads. For UNDERPINNING very light structures, the piles are driven along the structure and then brackets or CANTILEVER needles are provided to carry the structure.

2.

If the standards or not resting on the firm ground, the _________ of the standard should be provided and their bottom ends.(a) Bedding(b) Finishing(c) Raising(d) SpacingThe question was posed to me in an internship interview.My doubt is from Shoring and its Types in chapter Scaffolding, Shoring and Underpinning of Construction & Building Materials

Answer»

Right answer is (a) Bedding

For explanation: If standards are not resting on the FIRM ground, the base plates of suitable size should be provided at their bottom ends. Further, if required, TIMBER SOLE PLATE should be provided on which all base plates rest.

3.

The loading on the scaffolding decides the __________ of standards.(a) Bedding(b) Raising(c) Finishing(d) SpacingI had been asked this question during an interview.My doubt stems from Shoring and its Types in division Scaffolding, Shoring and Underpinning of Construction & Building Materials

Answer»

Correct option is (d) Spacing

The BEST explanation: The spacing of standards is less for HEAVY LOADING and more for light loading. The MAXIMUM spacing is about 3 metres.

4.

A large factor of safety should be adopted in the design of __________ as it is difficult to assess the actual loads.(a) Vertical shores(b) Pit method(c) Horizontal shore(d) Pile methodI have been asked this question in quiz.My enquiry is from Underpinning and its Types topic in chapter Scaffolding, Shoring and Underpinning of Construction & Building Materials

Answer»

Right option is (c) HORIZONTAL shore

The best EXPLANATION: In Flying or horizontal shore arrangement, the horizontal supports are given to the parallel walls which have become unsafe due to the removal or COLLAPSE of the intermediate building.

5.

_________ are the vertical members of the framework and they are either supported on the ground or embedded into the ground.(a) Ledgers(b) Standards(c) Putlogs(d) RakersThis question was posed to me in my homework.This interesting question is from Component Parts of a Scaffolding topic in portion Scaffolding, Shoring and Underpinning of Construction & Building Materials

Answer»

The correct answer is (b) Standards

For explanation: WHEREAS, PUTLOGS are the TRANSVERSE species which are placed on the Ledgers and which are SUPPORTED on the wall at one end. They are at the right angle to the wall. And the Ledgers are the horizontal MEMBERS parallel to the wall.

6.

__________ is a very light type of scaffolding and can be used only for the maintenance work such as painting, pointing, whitewashing, etc.(a) Trestle scaffolding(b) Suspended scaffolding(c) Patented scaffolding(d) Needle scaffoldingThis question was posed to me in final exam.My question comes from Component Parts of a Scaffolding topic in section Scaffolding, Shoring and Underpinning of Construction & Building Materials

Answer»

Correct choice is (b) Suspended SCAFFOLDING

Explanation: In Suspended scaffolding, the working platform is suspended from the roof by means of ropes, WIRES or chains and arrangements are made such that the platform can be raised or lowered. This type of scaffolding does not CREATE any obstruction on the ground and it is the most effective as it always PROVIDES the optimum level for working.

7.

In _________ method, the soil under the existing footing is consolidated by using chemicals.(a) Chemical consolidation(b) Freezing(c) Cement grouting(d) VibroflotationI have been asked this question by my college professor while I was bunking the class.Query is from Underpinning and its Types in section Scaffolding, Shoring and Underpinning of Construction & Building Materials

Answer»

Correct choice is (a) Chemical CONSOLIDATION

Best EXPLANATION: The procedure for chemical consolidation is as: The PERFORATED pipe are driven in an inclined direction. The inclination SLOPES are so adjusted that the ENTIRE area under the existing putting comes under the command of the inclined pipes; The chemical reaction takes place between two chemicals and the soil is consolidated.

8.

In __________ type of scaffolding, in place of timber, the Steel tubes can be effectively used for the scaffolding work.(a) Steel scaffolding(b) Patented scaffolding(c) Suspended scaffolding(d) Trestle scaffoldingThe question was asked by my school principal while I was bunking the class.This is a very interesting question from Component Parts of a Scaffolding in division Scaffolding, Shoring and Underpinning of Construction & Building Materials

Answer»

Correct answer is (a) Steel SCAFFOLDING

Best EXPLANATION: In steel scaffolding, the Steel tubes are available in standard lens with special coupling and set SCREWS. The scaffolding can be used upto any height. It is strong and more durable; it can be easily irritated and dismantle; it possesses high scrap VALUE and it is resistant to fire.

9.

In __________ method of underpinning, the existing wall is divided into suitable sections of width about 1.20 metre to 1.50 metre.(a) Pit Method(b) Pile Method(c) Miscellaneous Method(d) Chemical MethodThe question was asked in a national level competition.This question is from Underpinning and its Types topic in portion Scaffolding, Shoring and Underpinning of Construction & Building Materials

Answer»

The CORRECT answer is (a) Pit METHOD

To ELABORATE: In Pit Method, the holes are then made in the existing WALL. The needles with bearing plates and then inserted through this holes are supported on Jack. The pit is excavated and the existing foundation is taken up to the required LEVEL.

10.

________ is a piece which is used to bridge an opening in a wall and it supports one end of the putlog at the opening.(a) Transoms(b) Braces(c) Rope(d) BridleThis question was addressed to me in an interview for internship.This intriguing question comes from Component Parts of a Scaffolding in portion Scaffolding, Shoring and Underpinning of Construction & Building Materials

Answer»

The correct CHOICE is (d) Bridle

The best I can explain: Whereas, TRANSOMS are the Putlogs, but their both ends are supported on the Ledgers. And, Braces are the diagonals cross SPECIES fixed on the standards.

11.

In ___________ method, the underpinning is carried out by vibrating the sand.(a) Cement grouting(b) Vibroflotation(c) Chemical consolidation(d) FreezingI have been asked this question in class test.The above asked question is from Underpinning and its Types in chapter Scaffolding, Shoring and Underpinning of Construction & Building Materials

Answer»

Right choice is (b) Vibroflotation

To explain I WOULD say: Vibroflotation increases the DENSITY of soil which ultimately results in the increase of bearing capacity of soil. This method is useful for granular or SANDY soil and before the PROCESSING of underpinning START, the building or any of its structure components is shored carefully.

12.

The ____________ should be preferably Inclined at 45° with the ground.(a) Horizontal shore(b) Raking shore(c) Dead shore(d) Vertical shoreThis question was addressed to me during a job interview.Question is taken from Shoring and its Types topic in chapter Scaffolding, Shoring and Underpinning of Construction & Building Materials

Answer»

Right choice is (B) Raking shore

Explanation: However, in ACTUAL PRACTICE, the angle of INCLINATION in Raking or Inclined shore may vary from 45° to 75°. The top RAKER should not be inclined steeper than 75° with the horizontal.

13.

___________ type of Shoring is suitable for a maximum distance of about 9 m between the adjacent parallel walls.(a) Dead shore(b) Raking shore(c) Vertical shore(d) Flying shoreI had been asked this question in an interview for job.I'd like to ask this question from Shoring and its Types in section Scaffolding, Shoring and Underpinning of Construction & Building Materials

Answer»

Right option is (d) Flying shore

Easiest explanation: But when the DISTANCE is between 9 m to 12 m, a COMPOUND or Double Flying shore is provided. It should be seen that both the horizontal shores are SYMMETRICAL placed with respect to the FLOOR levels.

14.

In __________ type of scaffolding, the working platform is supported on movable contrivances such as Ladders, tripods, etc., mounted on wheels.(a) Trestle scaffolding(b) Cantilever scaffolding(c) Mason’s scaffolding(d) Bricklayers scaffoldingI had been asked this question in an interview for job.My question is from Component Parts of a Scaffolding in division Scaffolding, Shoring and Underpinning of Construction & Building Materials

Answer» RIGHT choice is (a) TRESTLE SCAFFOLDING

The explanation is: Trestle scaffolding is useful for minor repairs on PAINTING work inside the room and the maximum height of to REACH this type of scaffolding can be adopted is about 5 metre from the supporting surface.
15.

__________ type of scaffolding is used when the proper hard ground is not available for the standards to rest.(a) Steel scaffolding(b) Trestle scaffolding(c) Bricklayers scaffolding(d) Cantilever scaffoldingI have been asked this question in an interview for job.Question is from Component Parts of a Scaffolding topic in division Scaffolding, Shoring and Underpinning of Construction & Building Materials

Answer»
16.

When one building is higher than the other _____________ may be provided on the horizontal shores.(a) Raking shore(b) Pile Underpinning(c) Flying shore(d) Pit UnderpinningThe question was asked in an interview for internship.The query is from Underpinning and its Types topic in division Scaffolding, Shoring and Underpinning of Construction & Building Materials

Answer»

The correct option is (a) Raking shore

To elaborate: Whereas, the flying SHORES are generally erected at a distance of about 3 m to 5 m in plan and horizontal Struts are INTRODUCED, if necessary, to act as a lateral bracing between the adjacent line shores.

17.

__________ method is used to restore slab or pavement which has settled.(a) Vibroflotation(b) Freezing(c) Chemical consolidation(d) Cement groutingI have been asked this question in an interview for job.My doubt stems from Underpinning and its Types in section Scaffolding, Shoring and Underpinning of Construction & Building Materials

Answer»

Correct choice is (d) CEMENT grouting

Easy explanation: The OPERATION of Cement grouting is simple. The HOLES are drilled in a slab and then cement grout is forced under pressure through these holes. The pressure is maintained until the cement grout has set.

18.

The temporary framework is known as __________ and it is useful in construction demolition, maintenance or repair works.(a) Underpinning(b) Shoring(c) Scaffolding(d) GroutingThe question was posed to me in an interview for job.This is a very interesting question from Component Parts of a Scaffolding topic in portion Scaffolding, Shoring and Underpinning of Construction & Building Materials

Answer»

The correct choice is (c) Scaffolding

Best explanation: When the height above floor level exceeds about 1.5 m a temporary structure, usually of TIMBER, is ERECTED close to the work to PROVIDE a safe working PLATFORM for the WORKERS and to provide limited space for the storage of plant and building materials. This temporary Framework is known as scaffolding or simply of scaffold.

19.

_________ is a Board placed parallel to the Ledgers and supported between the Putlogs.(a) Toe board(b) Guard rail(c) Raker(d) BoltsI have been asked this question in semester exam.The query is from Component Parts of a Scaffolding in division Scaffolding, Shoring and Underpinning of Construction & Building Materials

Answer»

Correct choice is (a) Toe board

For explanation: Toe board is provided to WORK as a PROTECTIVE MEASURE on the working platform. Whereas, GUARD rail is a rail provided like a Ledger at the working level.

20.

In ___________ shores, the needles are placed at a distance of about 1.5 m to 2 m and they are suitably braced.(a) Vertical shores(b) Horizontal shore(c) Inclined shore(d) Raking shoreThis question was addressed to me by my college director while I was bunking the class.I need to ask this question from Shoring and its Types topic in chapter Scaffolding, Shoring and Underpinning of Construction & Building Materials

Answer»

Correct option is (a) Vertical shores

The best I can EXPLAIN: In vertical shores, the FOLDING wedges, sole plate, dogs and braces are USED. A Raking shore may be PROVIDED as an additional safety especially in case of weak walls.

21.

Sometimes the structures are to be temporarily supported. This is achieved by what is known as the _________(a) Scaffolding(b) Shoring(c) Underpinning(d) GroutingI had been asked this question in unit test.Question is taken from Shoring and its Types topic in section Scaffolding, Shoring and Underpinning of Construction & Building Materials

Answer»

Correct OPTION is (B) Shoring

Best explanation: Shoring is essential for STRUCTURES which have become UNSAFE due to an equal settlement of foundation or due to removal of the adjacent building or due to any other reason. For safe structures, The Shoring is required to prevent MOVEMENT when certain additions and alterations are being carried out.

22.

In ____________ method, the freezing pipes are driven below the existing footing and the soil is frozen.(a) Vibroflotation(b) Cement grouting(c) Chemical consolidation(d) FreezingThe question was asked by my school teacher while I was bunking the class.I would like to ask this question from Underpinning and its Types in section Scaffolding, Shoring and Underpinning of Construction & Building Materials

Answer»
23.

_________ method is useful when the soil consists of sand or granular material.(a) Vibroflotation(b) Chemical grouting(c) Chemical consolidation(d) FreezingI got this question in an interview for internship.Question is from Underpinning and its Types topic in chapter Scaffolding, Shoring and Underpinning of Construction & Building Materials

Answer»

Right CHOICE is (c) Chemical consolidation

To explain: Here, the cost of consolidation depends on the nature of SOIL, depth of consolidation, site of WORK, etc. In this method, the soil under the existing footing is CONSOLIDATED by using Chemicals. The chemical reaction takes place between two chemicals and hence the soil is consolidated.

24.

In ___________ arrangement, the horizontal members, known as the needles are supported by vertical members.(a) Horizontal shore(b) Flying shore(c) Dead shore(d) Raking shoreI had been asked this question during an online exam.My enquiry is from Shoring and its Types topic in section Scaffolding, Shoring and Underpinning of Construction & Building Materials

Answer»

Correct answer is (C) Dead SHORE

Easy explanation: In Dead shore ARRANGEMENT, the needles are driven at right angles to the wall through the holes made in the wall. A Dead shore is used when the lower part of the wall has become DEFECTIVE and the foundations are to be deepened.

25.

____________ is necessary to tie back the scaffolding with the building at suitable levels.(a) Loading(b) Tying-in(c) Raising(d) SpacingI had been asked this question during an online interview.My question is from Shoring and its Types topic in chapter Scaffolding, Shoring and Underpinning of Construction & Building Materials

Answer» CORRECT option is (b) Tying-in

To elaborate: Tying-in scaffold can be achieved in different ways: A vertical or horizontal TUBE, wedged by means of a rebel pn, may be PROVIDED in an opening and ONE of the ends of the PUTLOGS maybe coupled with this tube.
26.

The placing of new Foundation below and the existing foundation of the process of strengthening the existing Foundation is known as the ___________ of foundation.(a) Shoring(b) Underpinning(c) Grouting(d) ScaffoldingThis question was posed to me in an interview.I would like to ask this question from Underpinning and its Types topic in section Scaffolding, Shoring and Underpinning of Construction & Building Materials

Answer»

Right choice is (b) UNDERPINNING

The explanation: Following are the situations demanding underpinning: A building with DEEP Foundation is to be constructed at joint to an EXISTING building; The SETTLEMENT of existing Foundation has taken placed, resulting in serious cracks in the wall; The basement is to be PROVIDED to an existing building.

27.

In __________ arrangement, the horizontal supports are given two parallel walls which have become unsafe due to the removal or collapse of the intermediate building.(a) Inclined shore(b) Raking shore(c) Dead shore(d) Flying shoreThis question was posed to me during an online exam.I need to ask this question from Shoring and its Types in section Scaffolding, Shoring and Underpinning of Construction & Building Materials

Answer»

Correct choice is (d) Flying shore

For explanation I WOULD say: A Flying shore consists of WALL plate, needles, cleats, strut, straining pieces and folding wedges. The flying shore should have a DEPTH of not LESS than 1/13th of the clear span and width should not less than 1/15th of its length.

28.

_________ is stronger than the single scaffolding and it is used in the construction of stone work.(a) Trestle scaffolding(b) Steel scaffolding(c) Patented scaffolding(d) Double scaffoldingThis question was addressed to me in an interview.Origin of the question is Component Parts of a Scaffolding in division Scaffolding, Shoring and Underpinning of Construction & Building Materials

Answer»

Right option is (d) DOUBLE scaffolding

Easy explanation: In Double scaffolding or Mason’s scaffolding, the FRAMEWORK is similar to the single scaffolding accept that two rows of standards are provided. The distance between the face of the WALL and the first show of standard is about 200 MM to 300 mm and the distance between the two rows is about 1 m.

29.

___________ is the most common type of scaffolding and is widely used in the construction of brickwork.(a) Suspended scaffolding(b) Single scaffolding(c) Trestle scaffolding(d) Steel scaffoldingI got this question in class test.My question is from Component Parts of a Scaffolding topic in portion Scaffolding, Shoring and Underpinning of Construction & Building Materials

Answer»

The correct answer is (b) Single SCAFFOLDING

To explain I would say: Single scaffolding or Bricklayers scaffolding CONSISTS of a single row of standards placed at a distance of about 1.20 m from the WALL. The distance between the successive standards is above 2 metre to 2.50 m. The LEDGERS are then fixed to the standards at a vertical distance of about 1.20 metre to 1.80 metres.

30.

In ____________ shore arrangement, the inclined supports are given to the external walls from the ground.(a) Raking shore(b) Flying shore(c) Dead shore(d) Patented shoreThe question was posed to me in an interview for job.My question is based upon Shoring and its Types in section Scaffolding, Shoring and Underpinning of Construction & Building Materials

Answer»

The correct choice is (a) Raking shore

For explanation I would say: A Raking shore or Inclined shore consists of a wall PLATE, NEEDLES, plates, cleats, BRACING and sole plate. The wall plate is PLACED against the wall and is secured by the means of needles which penetrate into the wall for a distance of about 150 mm. The wall plate distributes the pressure EVENLY.