A _____________ is provided at the top of the Tremie to receive the concrete.(a) Bucket(b) Hopper(c) Tremie(d) PipeThe question was asked in an internship interview.My enquiry is from Placing of Concrete topic in section Cement Concrete Construction of Construction & Building Materials

Answer»

The CORRECT answer is (b) HOPPER

Easy explanation: It is NECESSARY to keep the bottom end of the Tremie sufficiently deep in the fresh concrete so as to prevent the entry of water in the Tremie. A Hopper is provided at the top to receive the concrete which GOES through the Tremie into the water.