A common footing provided for two or more columns is known as _________(a) Continues footing(b) Combined footing(c) Cantilever footing(d) Eccentric footingThis question was posed to me in semester exam.This intriguing question comes from Components topic in division Important Building Components of Construction & Building Materials

Answer»

Right answer is (b) Combined footing

To explain I would SAY: Combined footing becomes useful when an exterior column is situated NEAR the BOUNDARY line of the plot and it is not possible to PROJECT its footing symmetrically on both SIDES.