The following are the starting and ending times of activities A, B, C, D, E, F, G and H respectively in chronological order: “asbscsaedsceesfsbedegseefehsgehe”Here,xs denotes the starting time and xe denotes the ending time of activity X. W need to schedule the activities in a set of rooms available to us. An activity can be scheduled in a room only if the room is reserved for the activity for its entire duration. What is the minimum number of rooms required ?(A) 3(B) 4(C) 5(D) 6 |