1.

The first step in flooring is:(a) Topping(b) Base coat(c) Sand filling(d) R.C.C. layerThe question was asked in an internship interview.I'd like to ask this question from Floor Coverings topic in division Building Construction of Basic Civil Engineering

Answer»

Correct OPTION is (b) Base coat

For EXPLANATION I would say: FLOORING refers to the covering of FLOOR. Before laying any covering material, a base coat has to be provided. Cement concrete ratio of 1:8:16 of 100mm thick or COMPACTED earth of ratio 1:4:8 can be used.