A can do 75% of a job in 18 days and B can do 25%...
1.
A can do 75% of a job in 18 days and B can do 25% of the job in 12 days. If they work on it together, in how many days can they do 75% of the job?1). 162). 83). 204). 12
Answer»
ANSWER
for this
QUESTION
is
12
Show Answer