A, B and C can finish a job working alone in 20, 3...
1.
A, B and C can finish a job working alone in 20, 30 and 60 days respectively. They all work together for 1 day, then A and B quit. How many days C working alone will take to finish the remaining part of the job?1). 602). 543). 64). 27
Answer»
54
is the
ANSWER
Show Answer
Discussion
No Comment Found
Post Comment
Related InterviewSolutions
A, B and C can finish a job working alone in 20, 30 and 60 days respectively. They all work together for 1 day, then A and B quit. How many days C working alone will take to finish the remaining part of the job?1). 602). 543). 64). 27
Reply to Comment
×
Name
*
Email
*
Comment
*
Submit Reply
Your experience on this site will be improved by allowing cookies. Read
Cookie Policy
Reject
Allow cookies