X alone can do a piece of work in 15 days and Y alone can do it in 10 days. X and Y undertook to do it for Rs. 720. With the help of Z they finished it in 5 days. How much is paid to Z?

Answer»

X alone can do a piece of work in 15 days and Y alone can do it in 10 days. X and Y undertook to do it for Rs. 720. With the help of Z they finished it in 5 days. How much is paid to Z?