Workout the quantity of earthwork for an embankment 150 m long and 10 m wide at the top. Slide slop is 2:1 and depths at each 30 m intervals are 1.2, 1.4, 1.4, 1.6, 0.60, 1.6 m.(a) 3572.9 m^3(b) 4563.7 m^3(c) 2572.8 m^3(d) 2590.0 m^3 |
|
Answer» Right choice is (c) 2572.8 m^3 For explanation I would say: Solution- |
|