Which system of contract costing is employed in case where it is very difficult for the contractor to quote the contract price because there is no precedent which may be taken as the basis? a) Cost Plus b) Sub-Contractor c) Work-in-progress d) Work uncertified |
|
Answer» Correct option: a) cost plus |
|