Answer» Correct Answer - Option 2 : Measurement
To apply the preventive maintenance plan we have to do the following: - Study the production line of planning and plant area environment and the theory of the machine
- Divided the machines into many branches like gearboxes, bearing, hydraulic, pneumatic and etc...
- Start evaluation of the lubrication plan for all parts.
- Start establishing the daily, weekly, monthly and etc. maintenance tasks plans for the maintenance team and production teams for each machine
- Start establishing the daily testing (it a very important )
- Start to implement the system and collect the result to make the fine-tuning of this scandal according to the feedback from the downtime report.
- All of these steps depend on the recommendations of the machine's fabricators and your experience.
|