When does the next Sprint begin?

Answer»

The next sprint BEGINS immediately after the conclusion of the previous Sprint. A sprint begins with Sprint PLANNING meeting and concludes with Sprint Retro. In GENERAL, planning for the subsequent Sprint starts after the conclusion of the previous sprint. So, typically the plan for the next Sprint is fixed by the TIME the previous sprint ends. The actions from the RETROSPECTIVE and demo will go in the product backlog and can be prioritized in a future sprint.