Saved Bookmarks
| 1. |
What describes the data and control to be processed?(a) Planning process(b) Software scope(c) External hardware(d) Project complexityThe question was posed to me in class test.I'd like to ask this question from Project Planning topic in section Software Management of Software Engineering |
|
Answer» Correct choice is (B) Software scope |
|