| 1. |
The pit is typically at least ____________ deep and ___________ across.(a) 14 meters, 10 m(b) 30 meters, 15 m(c) 3 meters, 1 m(d) 11 meters, 9 mThe question was posed to me by my college professor while I was bunking the class.This key question is from Design of Septic Tanks in portion Road Estimating, Sanitary and Water Supply Work of Civil Engineering Drawing |
|
Answer» Correct OPTION is (c) 3 meters, 1 m |
|