1.

The future period for which the provision is made in designing the capacities of the various components of the sewerage scheme is known as the ______________(a) Design period(b) Manufacture time(c) Construction work(d) Repair work

Answer» The correct answer is (a) Design period

Explanation: The design period depends upon the following:

-Ease and difficulty in expansion,

-Amount and availability of investment,

-Anticipated rate of population growth, including shifts in communities, industries and

commercial investments,

-Hydraulic constraints of the systems designed, and

-Life of the material and equipment.