The future period for which the provision is made in designing the capacities of the various components of the sewerage scheme is known as the ______________(a) Design period(b) Manufacture time(c) Construction work(d) Repair work |
|
Answer» The correct answer is (a) Design period Explanation: The design period depends upon the following: -Ease and difficulty in expansion, -Amount and availability of investment, -Anticipated rate of population growth, including shifts in communities, industries and commercial investments, -Hydraulic constraints of the systems designed, and -Life of the material and equipment. |
|