Talk briefly on Reports in JIRA? |
|
Answer» To TRACK the progress in Agile, a Burndown Chart shows the actual and estimated AMOUNT of work to be done in the SPRINT. A typical burndown chart will look somewhat like this, where the red line indicates the actual task REMAINING while the blue line indicates ideal task remaining during the scrum cycle |
|