1.

Rohan takes twice the time taken by Sohan to complete a piece of work and half of the time taken by Mohan to complete the work. If all of them working together can complete the work in 12 days, in how many days Rohan and Sohan working together can complete that work?1. 10 days2. 12 days3. 14 days4. 16 days5. 20 days

Answer» Correct Answer - Option 3 : 14 days

Calculation:

Let the time taken by Sohan to complete the work = x days

Then, time is taken by Rohan to complete the work = 2x days and

Time is taken by Mohan to complete the work = 4x days

According to the question:  

⇒ \(12(\frac{1}{x}+{1}{2x}+{1}{4x})=1\)

⇒ \(\frac{4+2-1}{4x}=\frac{1}{12}\)

⇒ \(\frac{7}{4x}=\frac{1}{12}\)

⇒ x = 21 days

Time was taken by Sohan to complete the work = x = 21 days

Time taken by Rohan to complete the work = 2x = 2 x 21 = 42 days

Time taken by Mohan to complete the work = 4x = 4 x 21 = 84 days

Let the no of days taken by Rohan and Sohan to complete the work = p days

According to the question:

⇒ \(p(\frac{1}{21}+{1}{42})=1\)

⇒ \(p\frac{1+2}{42}=1\)

⇒ p = 14 days

∴ The number of days by Rohan and Sohan to complete the work is 14 days.