Ramesh can complete a work in 18 days while suresh take 9 days to complete the same work. They are paid rs. 900 on successfully completion work. When they work together. What is ramesh share in the amount. |
|
Answer» Answer: 300 Step-by-step EXPLANATION: ramesh can do 1/18 WORK in ONE day suresh can do 1/9 work in one day 1/9 + 1/18 = 1/6 so 6 days is required for together so 6*1/18 = 1/3 so 1/3*900 = 300 |
|