1.

P and Q can complete work in 6 days, Q and R can complete it in 12 days while P and R take 15 days to complete the same piece of work. If P and Q start working, in how many days total work will be completed if R works every fourth day?1. 5 days2. 6.05 days3. 8 days4. 7.5 days

Answer» Correct Answer - Option 2 : 6.05 days

Given:

P and Q can complete work in 6 days.

Q and R can complete it in 12 days.

P and R took 15 days to complete the same piece of work. 

R works every fourth day.

Concepts used:

Efficiency = Work/Time

Time = Work/Efficiency

Calculation:

1-day work of P and Q = 1/6

1-day work of Q and R = 1/12

1-day work of P and R = 1/15

1 days work of P, Q and R = 1/2[(1/6) + (1/12) + (1/15)]

⇒ 19/120

Work done by P and Q in 3 days = 3/6 = 1/2

Work done by P, Q and R till fourth day = 1/2 + 19/120 = 79/120 

Remaining work = 1 – (79/120) = 41/120

Time = Work/Efficiency

Time taken by P and Q to complete the remaining work = (41/120)/(1/6) = 2.05 days

Total time taken by P, Q and R = 4 + 2.05 days = 6.05 days

∴ P, Q and R complete the work together when P and Q are assisted R on every fourth day in 6.05 days.