Manisha can complete a job in 5 days. Manisha is twice as fast as Akshata while Akshata is thrice as fast as Nimisha. If all of them work together, then in how many days would the job be completed?1. 4 days2. 3 days3. 1 day4. 2 day |
|
Answer» Correct Answer - Option 2 : 3 days Given: Manisha can complete a job in 5 days. Formula Used: Total work = Efficiency × Time Calculation: According to the question: Manisha can do a piece of work in 5 days Akshata can do the same work in 10 days Nimisha can do the same work in 30 days. So together they can do the piece of work in 1 day ⇒ (1 / 5 + 1 / 10 + 1 / 30) ⇒ (12 + 6 + 2) / 60 ⇒ 20 / 60 ⇒ 1 / 3 ∴ If all of them work together the work will be completed in 3 days. |
|