longwill73. If 5 men can do a certain construction work in 14 days, then howmen taketo complete the same construction work? |
|
Answer» 5 men can do in 14 daysTotal amount of work=5×14=70 man-daysSo 7 men will take 70/7 =10 days to complete the same construction work |
|