| 1. |
Janshakti Constructions Limited undertakes to construct a road 1000 metres long in 50 days. It initially uses 56 road-rollers and finds at the end of 27 days that only 448 metres of the road has been built. How many more road-rollers must be used so that the work may be finished on schedule? |
|
Answer» Janshakti Constructions Limited undertakes to construct a road 1000 metres long in 50 days. It initially uses 56 road-rollers and finds at the end of 27 days that only 448 metres of the road has been built. How many more road-rollers must be used so that the work may be finished on schedule? |
|