James can do a piece of work in 25 days and Kishan can finish it in 20 days. They work together for 5 days and then James leaves. In how many days will Kishan finish the remaining work? |
|
Answer» James can do a piece of work in 25 days and Kishan can finish it in 20 days. They work together for 5 days and then James leaves. In how many days will Kishan finish the remaining work? |
|