Initially it was planned that 16 workers are required to build the wall in 48 hours. But due to some reason 4 workers did not show up for work. Now, the contractor wants the wall to be built in 32 hours. How many more workers are required to complete the job? |
|
Answer» Initially it was planned that 16 workers are required to build the wall in 48 hours. But due to some reason 4 workers did not show up for work. Now, the contractor wants the wall to be built in 32 hours. How many more workers are required to complete the job? |
|