1.

In the next six questions there is no negative marking. The best answer carries one mark while other answer choices carry less than one mark. Q80. You are the chief manager of an important project. There are six fairly independent parts of the project requiring different mix of skill set and knowledge base. The six parts are handled by different team leaders. At this time four of the teams are progressing well with their assigned parts. However, two teams are behind schedule and if this state of affairs continues the project would have time overrun. Part of the problem lies in the fact that some staff members in these two behind schedule teams have left the organization without replacement. In the situation what action should you take? 1. Talk to the two teams to collectively analyses what is the problem. 2. Hold the two team leaders to be responsible for delay and think of replacing them. 3. Inform higher management about the developments and request filling the vacant positions. 4. Explore the possibility of outsourcing some part of the work.

Answer»

In the next six questions there is no negative marking. The best answer carries one mark while other answer choices carry less than one mark.

Q80. You are the chief manager of an important project. There are six fairly independent parts of the project requiring different mix of skill set and knowledge base. The six parts are handled by different team leaders. At this time four of the teams are progressing well with their assigned parts. However, two teams are behind schedule and if this state of affairs continues the project would have time overrun. Part of the problem lies in the fact that some staff members in these two behind schedule teams have left the organization without replacement. In the situation what action should you take?

1. Talk to the two teams to collectively analyses what is the problem.

2. Hold the two team leaders to be responsible for delay and think of replacing them.

3. Inform higher management about the developments and request filling the vacant positions.

4. Explore the possibility of outsourcing some part of the work.