1.

In earthwork per 28.30 cu m, how many beldars and mzdoors are required per day?(a) 15 Beldars and 8 Mazdoors(b) 0 Beldars and 14 Mazdoors(c) 2 Beldars and 0 Mazdoors(d) 5 Beldars and 4 Mazdoors

Answer» The correct option is (d) 5 Beldars and 4 Mazdoors

Best explanation: Excavation in foundation, trenches, etc. in ordinary soil including disposal up to 30 m(100’) and lift of 1.5 m (5’).