if 6 man can do a piece of work in 30 days of 9 hours each, how many men will take to do 10 times the amount of work if they work 25 days of 8 hour each |
|
Answer» Answer: 6×30×9=25×8×x/10 x= 6×30×9×10/25×8 |
|