| 1. |
If 5 workers take 12days to weed a field how many will 6 workers take |
|
Answer» HEYA ! 5 workers - 12 days 6 workers - ? ( cross MULTIPLY ) = 6×12/5 = 72/5 = 14.4 days HOPE this helps you and I think your question is wrong |
|