If 49men can dig a well 28m deep in 52 days how many men will be required to dig a well 40m deep in 35days

Answer»

104 men will be required.

Step-by-step explanation:

28m well can be DUG in 52 days by 49 men

1m well can be dug in 52 days by 49/28 men

1m well can be dug in 1 day by 49×52/28 men

40m well can be dug in 1 day by 49×52×40/28 men

40m well can be dug in 35 days by

49×52×40/28×35men

= 104 men .