If 49men can dig a well 28m deep in 52 days how many men will be required to dig a well 40m deep in 35days |
Answer» 104 men will be required.Step-by-step explanation: 28m well can be DUG in 52 days by 49 men 1m well can be dug in 52 days by 49/28 men 1m well can be dug in 1 day by 49×52/28 men 40m well can be dug in 1 day by 49×52×40/28 men 40m well can be dug in 35 days by = 104 men . hope it helps mark me as Brainliest please |
|