| 1. |
If 24 men can do a piece of work in 18days. how many men are required to complete the same piece of work in 12 days |
|
Answer» 24 men can do in 18days X men can do the same work In 12 days Do the CROSS MULTIPLICATION X=(12*24)/18=16men |
|